Northeast Corridor Track Modernization Program
The Northeast Corridor Track Modernization Program is a series of projects to improve the tracks along the NEC. The work is taking place now through mid-December and starts again in early March of 2019. The end result of this work will be a more reliable ride with improved ride quality.
Progress & Passenger Impact
During the course of 2018, Amtrak expects to replace over 80 miles of welded rail, install over 110,000 concrete ties, and tamp over 300 miles of track in the Northeast Corridor.
How will it impact my commute?
If you travel along the NEC regularly, you may have already noticed your train slowing down along certain sections of your journey, large yellow construction vehicles on the tracks or several men/women with yellow vests standing trackside. Wonder what this is all about? Amtrak is working on the railroad. As a result of our maintenance efforts, some train schedules have been adjusted and additional delays are possible as segments of track are removed from service or train pass work areas.
What kind of work is being done?
Amtrak has a full fleet of construction equipment to aid in maintaining the railroad. From the track laying machine, to the tamper, see below to learn how Amtrak is working to improve the NEC.
46,140
feet of catenary hardware updates
110,000
concrete ties installed
1,261
bridge ties replaced
293
miles of high speed surfacing
50
track miles of undercutting completed
40
track miles of rail installed
How do I stay informed?
To check the status of your train or to modify existing reservations, visit Amtrak.com or the Amtrak mobile app.
- Opt-in to email or text alerts when booking your trip to be notified of real-time delays
- Follow @AmtrakNECAlerts for timely updates about service along the NEC